Sidewalk Design Drawings (pdf): Overview | Sidewalk Detail 1 2 3 5-foot wide sidewalk entire length of Calvin Lane on the south/east (odd-numbered) side 2-foot wide buffer between curb and sidewalk Driveway aprons will be replaced 26 trees expected to be removed 30 trees planted as replacements, per the City’s Street Tree Master Plan Sidewalk Design Drawings (pdf): Overview | Sidewalk Detail 1 2 3
4-foot wide sidewalk entire length of Calvin Lane on the south/east (odd-numbered) side 2-foot wide buffer between curb and sidewalk except at Lot 17 (513 Calvin Lane), where buffer decreases to 0 feet in order to preserve two large trees Driveway aprons will be replaced 24 trees expected to be removed 29 trees planted as replacements, per the City’s Street Tree Master Plan
|