Baltimore Road is a major roadway that connects the east side of the City of Rockville to Rockville Town
Center. The road improvements standardized the roadway section to make it safer, added pedestrian
safety measures at several intersections, and created easier access to the Rockville Metro station. To
protect the environment, the project followed Federal and State Environmental Requirements published
by the Maryland State Highway Administration (SHA).
Improvements
Improvements between South Stonestreet Avenue and Norbeck Road enhanced safety for pedestrians by improving crossings and adding sidewalk and bicycle facilities on South Stonestreet Avenue. Improvements between Route 28 and the city limits standardized the roadway section and added accessibility along the 1.25-mile section of Baltimore Road.
After Photos
Project Budget
$7.7 million, $3.6 million of which was covered by a grant.
Project Timeline
-
SurveyingDecember 2009 – February 2010
-
Initial Public MeetingFeb. 3, 2010
-
Preliminary DesignsSummer 2010
-
Second Public MeetingSept. 29, 2010
-
Design (90% Completed)May 2016
-
Design (100% Completed)Fall 2018
-
SHA Grant ApprovalsFebruary 2020
-
Bidding and AwardSummer and Fall 2020
-
“City Eyes Start of Baltimore Road Improvements”February 2021
View the Rockville Reports article.
-
Construction BeganMarch 2021
-
“(Road) Signs of Spring: Baltimore Road Construction Commences”April 2021
View the Rockville Reports article.
-
“Portion of Baltimore Road to Close Until October”June 2021
View the Rockville Reports article.
-
“Baltimore Road Work Continues as Schools Return to Session”August 2021
View the Rockville Reports article.
-
“Baltimore Road Closure and Detour to Remain Through November”October 2021
View the Rockville Reports article.
-
“Construction Continues on Baltimore Road Project as Roadway is Set to Reopen”November 2021
View the Rockville Reports article.
-
“Baltimore Road Reopens as Improvement Project Continues”December 2021
View the Rockville Reports article.
-
“With Weather Warmup, Construction to Ramp Up on Baltimore Road”May 2022
View the Rockville Reports article.
-
“Baltimore Road Project Enters New Construction Phase”September 2022
View the Rockville Reports article.
-
“Baltimore Road Partially Resurfaced as Corridor Improvements Continue”November 2022
View the Rockville Reports article.
-
“Shared-Use Path Complete as Baltimore Road Corridor Improvements Continue”January 2023
View the Rockville Reports article.
-
“Baltimore Road Corridor Improvements Near Completion”April 2023
View the Rockville Reports article.
-
Substantial Construction CompletionMay 2023
-
“Long and Winding Baltimore Road Construction Concludes”July 2023
View the Rockville Reports article.
Contact
Andrew Luetkemeier
Public Works Department
Traffic and Transportation Division
240-314-8524
aluetkemeier@rockvillemd.gov
Hours
Monday – Friday
8:30 a.m. – 5 p.m.
Address
Rockville City Hall
111 Maryland Ave.
Rockville, MD 20850